Construction Projects

 const zone  Bay City Construction Map
       cone        Construction in Bay County

Sidewalk Repairs are Coming Soon!
A 15-year sidewalk repair plan is being developed to repair the failing sections of sidewalk throughout the City.  In 2015-2016, the City conducted an inventory of all the sidewalks in the City and noted each area that should be repaired.  The order of locations will be determined in accordance with the 2016 Bay City Housing Study.  This is an overall view that looks at needs for overall infrastructure in the City in order to determine where the work will begin and when it will be scheduled.  The plan is in development stages, but we are hoping to begin repairs by August.
 
  1. Rachel Phillips, P.E.

    Municipal Engineering Manager

Construction Quick Links

Midland Business District Improvements, Henry to Litchfield 
Midland Bus Dist
 
 
 
 
 
  
  • Construction Dates:  July 31 – October 28, 2017
  • Construction Low Bid:  $822,369.20
  • Detour on Vermont, Catherine, John, and Walnut (Walnut to Litchfield will remain open with intermittent lane closures.
Midland Street Presentation 

The project includes complete street reconstruction from Henry to Walnut, including new sewer (separation of sanitary and storm sewers), water main, sidewalks, curb and gutter, and street lighting.  The street will be resurfaced with asphalt and receive new street lighting from Walnut to Litchfield, without changes to the curb and gutter, sidewalk, and utilities.  The project is being funded with electric, water and sewer utility funds, TIFA funding and Street funding.  Shaw Contracting was the low bidder.
Farragut Street Watermain Replacement, 32nd to Fremont
  • Construction Dates:  July 10 - 28, 2017   Farragut
  • Construction by City Forces
  • Street will remain open with intermittent lane closures

This project includes the replacement of the watermain with a history of breaks on the east side of Farragut. 


 

Independence Bridge Repairs        indy bridge

  • Construction Dates:  September 2017 – April 2018 
  • Construction Estimate:  $1,095,000
  • Detour (December – March) on Liberty Bridge
This project includes replacement of the Bascule span deck grating, span stringers, and sidewalks.  The project is being funded with Federal, State and local funding.  This project is scheduled to be bid through MDOT on July 7.      
City Hall Parking Lot improvements                   complete green
  • Construction Dates:  April 17 – June 2, 2017
  • Construction Low Bid:  $286,918.55
  • Project is Complete and Open
  • The project includes reconstruction of the lot on the west side of Saginaw Street to complete removal of the Electric substation.  There will be new curbing, pavement,  and an improved Saginaw Street pedestrian crossing facility (construction of the pedestrian island is complete).  Shaw Contracting was the low bidder.
       
  •  Midland/Vermont S-Curve Resurfacing, Wenona to Dean
    • Construction Dates:  May 1 – June 29, 2017          complete green
    • Construction Low Bid:  $258,630.40
    • Project is Complete
    • Detour (May 1- June 9) on Henry St., Thomas/Jenny Streets (M-25), and Euclid Avenue (M-13)

    The project includes roadway asphalt milling and resurfacing, water main, curb and gutter, and sidewalks.  Shaw Contracting was the low bidder.     

     
       
         
    2016-17 Sidewalk Repairs  sidewalk repaired 
    2016 construction contract for the sidewalk repairs funded by Community Development Block Grant funds in Ward 8 are complete.  Environmental studies are underway to move to other Wards, if funding is available.  Affordable Contracting was the low bid contractor.  
    2016-17 Miscellaneous Concrete Repairs 

    The 2016 construction contract for miscellaneous concrete repairs (curb and gutter, pavement, etc. from utility work) are expected to be completed by mid July.  Tri-Valley Contracting was the low bid contractor. 


    Patterson Avenue Resurfacing, Marquette to Smith Patterson

    Construction Dates:  August 28 - October 30, 2017

    Construction Low Bid:  $478,124

                                      Detour on Marquette, Transit, and Smith 

    The project includes milling and resurfacing the existing asphalt, curb and gutter, watermain, and storm sewer placement.  Federal funding is secured for the project.  The low bidder in the MDOT May 5th letting was Rohde Brothers.  


      
    Fillmore   Fillmore Place, Trumbull to Park  

    • Construction Dates:  September 2017
    • Construction Estimate:  $925,000
    This project includes complete street reconstruction, new storm sewer, new water main, curb and gutter and sidewalk repairs.  The project is being funded with water and sewer utility funds.  The design is in process.  Construction dates and detour route have not yet been determined.  

    Midland Street Lead Watermain Replacements
    • Construction Dates:  May 1 – June 2, 2017
    • Construction by City Forces                            complete green
    • Project is Complete    

    The Water Distribution Division will be performing water system improvements at three intersections on Midland Street including Kiesel Street, Warner Street, and Chilson Street.  New 8” watermain will be installed at each intersection to replace existing 1.5” lead pipe watermains. This project has been identified in our lead abatement program and will improve water quality and fire flow to residents in this vicinity. 


     

     

     

    Site Tools